JOURNALISTS today asked Prime Minister Andrej Plenković about Mate Rimac's robotaxi project, which was financed from the National Recovery and Resilience Plan (NRRP).
Has the Much Anticipated Croatian Robotaxi Failed? - Total Croatia
September the 2nd, 2026 – Has the Croatian robotaxi story ended? It has been revealed that Mate Rimac’s Verne may need to return 89.7 million euros if it is determined that the project has indeed failed. The company Verne, which has been engaged in developing the much anticipated robotaxi project, is prepared to return 89.7 ... The post Has the Much Anticipated Croatian Robotaxi Failed? appeared first on Total Croatia.
The Zagreb robotaxi project by the company Project 3 Mobility, now Verne, led by entrepreneur Mate Rimac, was supposed to be completed by August 30, 2026.
Prime Minister Andrej Plenković has finally spoken out about the fiasco of Rimč's robotaxis. But instead of a clear answer about the state's responsibility, we got an attempt to relativize the problem by claiming that the entire NPOO cannot be reduced to one project and that Croatia will fulfill 404 out of 406 projects. That may be true, but it is not the answer to the question of what happened to...