EGENCO starts restoration of 20MW Nkula B Unit 6
By Rahim Abdul Malawi will soon regain 20 megawatts (MW) of electricity generation capacity by the end of October as the Electricity Generation Company (EGENCO) begins restoring Unit 6 at Nkula B Hydropower Station after a five-week breakdown. EGENCO says in a statement that restoration works started following the arrival of a critical spare part, […]
EGENCO Begins Restoration of 20MW Nkula B Unit 6
ShareBy Suleman Chitera, MFN ReporterOctober 4, 2026 | 5:49 AM Lilongwe, Malawi — The Electricity Generation Company (EGENCO) has commenced restoration works on the 20-megawatt (MW) Unit 6 at Nkula B Hydropower Station, which has been offline for five weeks following a breakdown. EGENCO says the restoration follows the arrival of a critical spare part,… The post EGENCO Begins Restoration of 20MW Nkula B Unit 6 appeared first on Malawi Freedom Ne…
Coverage Details
Bias Distribution
- There is no tracked Bias information for the sources covering this story.
Factuality
To view factuality data please Upgrade to Premium