A Tender Has Been Announced for the Establishment and Expansion of Wind Power Capacity.
8 Articles
8 Articles
The submission deadline is October 30th, and the results will be published no later than December 13th.
The new investment era for Hungarian wind farms is on track: in the recently announced tender, developers will be given the opportunity to build 702 megavoltamperes (MVA) of new capacity. However, the final tender conditions raise serious questions even before the start, as several changes have been made compared to the draft announced in the summer that increase the burden on investors, while the advantage of more prepared developers may also d…
The network will only be opened to new projects from 2030. The full article is available on the Electric Vehicles page under the title Wind power tender has been announced, new wind power plants can be built in these settlements. Other writings by the author: FSW (supervised).
The Hungarian Energy and Public Utilities Regulatory Authority (MEKH) has announced a tender for the construction of new wind farms and the expansion of the capacity of existing units, with a total of 702 megavoltamperes (MVA) of free capacity on the medium and high voltage grid being allocated to the winning investors.
A new chapter may open in the history of Hungarian wind energy: the tender for the establishment and expansion of wind power capacity has been announced. A total of 702 megavolt-amperes of capacity will be allocated at nine network nodes, and applications can be submitted until October 30.
From the beginning of September to the end of October, the opportunity to establish and expand wind power capacity is open.