TeraWulf Expands Contracted Power Capacity at Its Muskie Data Campus to 1 GW
8 Articles
8 Articles
TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW
Amended Kentucky Power agreement advances the second 500 MW phase into 2029 amid strong customer interest
TeraWulf doubles Kentucky data center power deal to a full gigawatt
Kentucky Power agreed to move TeraWulf's second 500-megawatt phase at Muskie up a year, to 2029, while Oracle's 1.3-gigawatt Wisconsin campus awaits a restarted grid review that could stretch past 2028.
TeraWulf raised the contracted power to 1 GW for its Muskie campus in Kentucky, where it plans to build AI facilities and high-performance computing by stages. The company has also planned to reach 2 GW, although that goal does not yet have announced energy contracts.
TeraWulf doubles Muskie power agreement to 1 GW
An extra 500 megawatts of promised electricity has moved the timetable for an eastern Kentucky AI campus forward, although the new delivery year depends on state approval. TeraWulf Inc. (NASDAQ: WULF), the U.S. data centre developer and bitcoin miner, said on Oct. 5 it amended its electric service agreement with Kentucky Power to raise contracted capacity to one gigawatt. The utility is developing a substation to serve Muskie. Muskie's second 50…
TeraWulf doubles contracted power at Muskie AI/HPC campus to 1 GW
TeraWulf doubled contracted power at its Muskie AI/HPC campus in Eastern Kentucky to 1 GW and plans to scale the site to as much as 2 GW.