News of the Day and the Hour Latest News of today The removal of rubble after the double earthquake of two months ago in Venezuela is a process that can take up to a year to complete, warn experts and the government of Delcy Rodríguez, while the reconstruction remains a pending project when thousands of people remain in shelters or improvised shelters. The Chavista Executive has enabled 14 Temporary Distribution Centers (CDT) in the state of La…
The cleaning of rubble and the demolition of collapsed structures after the earthquakes of magnitude 7.2 and 7.5 recorded on June 24 will take approximately one year, according to estimates of the Venezuelan Chamber of Construction (CVC). Two months after the seismic event, the reconstruction of the affected areas in the state of La Guaira [...] The entrance Chamber of Construction previews a year of cleaning work in La Guaira #24Ago was first p…
Drafting (ALN).- In parallel to the work of removal in the collapsed structures, the Ministry of People's Power of Public Works, in conjunction with the Mission Venezuela Bella Foundation, activated a phase of integral rehabilitation in the residential complex Agustina del Mar. The intervention of this urbanism made up of 70 apartments of two floors divided into [...] The entrance Advances the recovery in La Guaira: They remove more than 50% of …
Of the 500,000 tons of waste that have been transferred to the processing centers, only about 40,000 have been crushed in 57 days of operations. The post At least a year could delay the process of collecting and shredding debris in La Guaira appeared first on EL NATIONALA.
Coverage Details
Bias Distribution
- There is no tracked Bias information for the sources covering this story.
Factuality
To view factuality data please Upgrade to Premium