Second Breakthrough in Palghar for Mumbai-Ahmedabad Bullet Train

The MT-6 tunnel in Palghar is 47% complete using New Austrian Tunneling Method, part of 27.4 km of tunnels for the 508-km Mumbai-Ahmedabad bullet train, officials said.

  • On Tuesday, the Mumbai-Ahmedabad high-speed rail corridor recorded its second tunnel breakthrough in Palghar district, with the 454 m long and 14.4 m wide MT-6 tunnel nearly 47% complete.
  • Because geology was irregular, engineers employed the New Austrian Tunnelling Method using controlled drill-and-blast and excavation from both ends as tunnel boring machines were unsuitable.
  • Railways officials reported the excavation timeline as 12 months, with seven mountain tunnels in Palghar and eight surface tunnels overall under construction.
  • Track laying and electrification are advancing, and officials say the Surat-to-Bilimora section is slated to open on August 15, 2027.
  • Cost revisions show the estimate rising to Rs 1.98 lakh crore, and as of January 27, 2026, about 334 km of viaducts, 17 river bridges, and 12 major crossings are complete, with a December 2029 completion target.
Insights by Ground AI

14 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 66% of the sources lean Right
66% Right

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

The News Mill broke the news in on Tuesday, February 3, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal