Oracle Cites ‘Force Majeure’ to Shield Itself on Data Center, Bloomberg News Reports

Oracle wants the right to delay payments if Project Jupiter misses its 2028 opening after pipeline delays raised cost concerns, Bloomberg News reported.

  • On Thursday, Oracle sent a "force majeure" notice to developer Blue Owl Capital regarding Project Jupiter, its 1,400-acre AI data center in New Mexico, causing shares to fall around 4 per cent in premarket trading.
  • The New Mexico State Land Office twice rejected pipeline rights-of-way, with Land Commissioner Stephanie Garcia Richard citing emissions and resource strain; Energy Transfer subsequently rerouted the 17.8-mile pipeline across federal land.
  • Project Jupiter supports the Stargate programme to build computing power for OpenAI, potentially costing up to $165 billion; Oracle seeks to delay payments if the campus fails to open in 2028 as planned.
  • Oracle claimed as recently as August that Project Jupiter remained on schedule, yet the notice provides coverage if timelines shift; the pipeline's start date has been pushed to February.
  • Designed to run 2.5 gigawatts of Bloom Energy fuel cells, the facility's success depends on whether the revised pipeline route secures approval to meet the 2028 operational deadline.
Insights by Ground AI

17 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 75% of the sources are Center
75% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

IBTimes broke the news in New York, United States on Thursday, September 24, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal