New Mexico Supreme Court denies petitions regarding Project Jupiter air quality permit, water use

The court rejected environmental challenges and lifted a pause on permitting, leaving Project Jupiter with favorable rulings in both cases.

Summary by KVIA
(KVIA) -- Thursday, the New Mexico Supreme Court denied the request for a writ of mandamus requested by the New Energy Economy against the state Environment Department regarding an air quality permit application for the Project Jupiter data center. The data center is under construction in the Santa Teresa area. Additionally, the court denied a

5 Articles

Two resources were rejected, including one on the use of water for the data center being built in Doña Ana.

Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 75% of the sources are Center
75% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Telemundo Nuevo México broke the news on Thursday, September 17, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal