From Shuttered Coal Plant to Gigascale Battery: AGL Commissions First Stage of Giant Liddell BESS
Summary by Renew Economy
4 Articles
4 Articles
AGL begins commissioning first 250 MW of Liddell battery in Hunter Energy Hub
Sydney-headquartered gentailer AGL has begun commissioning of the first 250 MW of the 1,000 MWh Liddell Battery at the Hunter Energy Hub in New South Wales.Sydney-headquartered gentailer AGL has begun commissioning of the first 250 MW of the 500 MW / 1,000 MWh 2-hour grid-scale Liddell Battery at AGL’s Hunter Energy Hub in New South Wales (NSW). Construction of the battery, which sits next to the closed Liddell Power Station, approximately 230 k…