Sibiu–Pitești Motorway: Asphalt Works Started on an Experimental Section Section of Cornetu–Tigveni
10 Articles
10 Articles
VIDEO Sibiu-Pitești motorway: asphalts on the Cornetu-Tigveni segment. The work stage has reached 18%. The builders of section 3 Cornetu-Tigveni of the A1 Sibiu-Pitești motorway began to wipe out the first layers of asphalt, for the moment on an experimental section of 400 meters. The test will establish the asphalt recipe that will be used on the 37.4 kilometers of the section. The physical stage of the project has reached about 18%, but the wo…
The works at the Sibiu-Pitești Motorway (A1) advance to Section 3 Cornetu-Tigveni, where the builders began the asphalting of an experimental section. According to the information transmitted by Cristian Pistol, the director general of the National Road Infrastructure Management Company (CNAIR), the entrepreneur began the sanding of the asphalt on a sector between kilometers 71 and 71+400. The works are carried out in two layers [...] Article Si…
Work began on an experimental section of the Sibiu – Pitești Highway: , overall, the physical stage of the work reached approximately 18% . Work began on an experimental section of the Sibiu – Pitești Highway: , overall, the physical stage of the work reached approximately 18% . The asphalt works began on an experimental section of section 3 of the Sibiu – Pitești Highway (A1), between Cornetu and Tigveni Highway. The work was carried out by the…
The association of Italian and Romanian builders (Webuild - Tancrad) began the asphalt work on an experimental section 3 section of the Sibiu - Pitesti motorway (A1), between Cornetu and Tigveni,...
The works are progressing on section 3 Cornetu–Tigveni of the Sibiu–Pitești Highway (A1), where the builder began the renovation of the asphalt on an experimental stretch of 400 meters, between km 71 and km 71+400, announces Cristian Pistol, director general of the National Road Infrastructure Management Company. The operation, carried out in two successive layers, will contribute to the establishment of the final recipe [...]
An important new step was taken on the Sibiu Highway – Pitești site. The National Road Infrastructure Management Company announced that asphalt works began on an experimental section of 3 Cornetu – Tigveni section. According to information provided by Cristian Pistol, the director general of CNAIR, the association of Italian and Romanian builders Webuild [...]