Construction of the Motorway Bridge Has to Be Replanned: Full Lock of the A59 Near Bonn in the Summer of 2026

Summary by ga.de
The planned express construction method for the new A59 bridge near Bonn‐Geislar fails due to the tight time frame: the necessary permits cannot be obtained in time. Therefore, Autobahn GmbH has to completely re-plan – with longer construction time and later completion date.

2 Articles

Center

The planned express construction method for the new A59 bridge near Bonn‐Geislar fails due to the tight time frame: the necessary permits cannot be obtained in time. Therefore, Autobahn GmbH has to completely re-plan – with longer construction time and later completion date.

In fact, the Bundes Autobahn GmbH wanted to start working on a new bridge at the Bonn-Nordost motorway triangle this autumn. However, this has been done for the time being.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources are Center
100% Center

Factuality 

To view factuality data please Upgrade to Premium

Ownership

To view ownership data please Upgrade to Vantage

ga.de broke the news in on Wednesday, October 1, 2025.
Sources are mostly out of (0)
News
For You
Search
BlindspotLocal